Large-scale project
Steel · Pesquería, Nuevo León
Scrap Yard
Client Ternium
Erection of three gantry cranes, a cutting-machine support structure, and electrical and communication installations.
- Gantry crane erection: erection of 2,500 tonnes of heavy and medium-heavy structures for three gantry cranes.
- Crane electrical and communication installations: 52,246.95 metres of power supply cabling, 280 metres of power busbars with six phases and one earth, 14,426 metres of communication cabling, 3,250 metres of cable trays and main circuit breakers.
- Cutting-machine structure erection: erection of 300 tonnes of medium-heavy structure for a pantograph scrap-cutting machine.
- Cutting-machine electrical and communication installations: 1,485 metres of power supply cabling, 3,925 metres of communication cabling and 526 metres of cable trays.